Tuesday, June 6, 2017

Site visit-Pre-bore bent 2



Arrow Drilling was onsite to Pre-bore holes for bent 2, work pad that contractor had built was too soft. contractor put down tree logs for drill rig to set on.



Driller was setup and started Drilling at 9:30, drill started hitting rock at the start and continued.



Coffer dam was built really close to bore locations as shown in this picture


Monday, May 15, 2017

Site visit- First day


Contractor was onsite today, they where clearing on the south side of bridge site.

 
 
Construction signs where in place as well
North sign
 
 
South signs