Contractor had most of the rip rap in, a couple areas still needing rip rap.
Monday, July 31, 2017
Site visit-Check Compaction
8:20 Contractor had dump truck onsite, we started checking compaction. There was some soft spots, I had them dig them out and try again.
Contractor had most of the rip rap in, a couple areas still needing rip rap.
Contractor had most of the rip rap in, a couple areas still needing rip rap.
Thursday, July 13, 2017
Site visit-Poured Bent 3 & 4 Caps
Tuesday, July 11, 2017
Site visit, Poured Bent 3 Wall
Contractor was ready to pour Bent 3 Wall
Concrete arrived at 8:57, I tested concrete: Slump 2 1/2", Air 5%, Temp 79°
Finished pouring and headed back at 11:10
Concrete arrived at 8:57, I tested concrete: Slump 2 1/2", Air 5%, Temp 79°
Finished pouring and headed back at 11:10
Thursday, July 6, 2017
Site visit-Bent 4 Cap pour
2:36pm- Bent 4 cap and wall built and rebar basket is set in place ready for concrete pour
3:09pm- Pouring concrete at bent 4
Subscribe to:
Posts (Atom)