Thursday, July 13, 2017

Site visit-Poured Bent 3 & 4 Caps

 Contractor was ready to pour Caps for both Bents 3 and 4

 
 
 

 Concrete arrived at 8:05, I tested concrete: Slump 4 1/2", Air 5.5%, Temp 80°, I made four cylinders.









 Finished pour at 9:20, pour went good.