Collins Herman was onsite to install guardrail.
Monday, August 7, 2017
Tuesday, August 1, 2017
Site visit-Guardrail
Collins was onsite to put up guardrail post today
will let me know when they are planning on installing the guardrail
Monday, July 31, 2017
Site visit-Check Compaction
8:20 Contractor had dump truck onsite, we started checking compaction. There was some soft spots, I had them dig them out and try again.
Contractor had most of the rip rap in, a couple areas still needing rip rap.
Contractor had most of the rip rap in, a couple areas still needing rip rap.
Thursday, July 13, 2017
Site visit-Poured Bent 3 & 4 Caps
Tuesday, July 11, 2017
Site visit, Poured Bent 3 Wall
Contractor was ready to pour Bent 3 Wall
Concrete arrived at 8:57, I tested concrete: Slump 2 1/2", Air 5%, Temp 79°
Finished pouring and headed back at 11:10
Concrete arrived at 8:57, I tested concrete: Slump 2 1/2", Air 5%, Temp 79°
Finished pouring and headed back at 11:10
Thursday, July 6, 2017
Site visit-Bent 4 Cap pour
2:36pm- Bent 4 cap and wall built and rebar basket is set in place ready for concrete pour
3:09pm- Pouring concrete at bent 4
Thursday, June 29, 2017
Site visit-Pre-bore Bent 3
Arrow drilling was in place when i arrived at noon
Contractor had to rebuild the approach and cut off coffer dam so the drill rig could reach hole locations.
Drillers hit good rock in holes
Contractor had to rebuild the approach and cut off coffer dam so the drill rig could reach hole locations.
Drillers hit good rock in holes